BT Fibre Optic Broadband update

Dear Keston Resident
Kevin McNulty, Director Infrastructure Engagement at Openreach has advised Peter Zieminski that the additional cabinet required for Fibre Optic Broadband supply is being installed on Monday the 21st March and it will be completed on Thursday the 24th March. Power will be supplied to the cabinet on the 29th March and final commissioning and testing will take place on Friday the 1st April (no this date is not a joke!) – if all goes to plan orders can be placed from the 15th April !
Our thanks to Peter Zieminski who has tirelessly kept on chasing BT.